Tuesday, September 04, 2007

Bridge Reopens for Tuesday's Commute

Construction crews working on the San Francisco-Oakland Bay Bridge finished their project and reopened the bridge ahead of schedule. The job, which closed the busiest toll bridge in the nation for most of the Labor Day weekend, was for the demolition a 350-foot section of the upper deck of the bridge just east of Yerba Buena Island and to roll a new, 6,700-ton section into place. Caltrans closed the bridge at 8 p.m. Friday and set aside 81 hours for contractor C.C. Myers Inc. to finish the job in time for this morning's commute.